Rcox220
Civil/Environmental
- Feb 3, 2011
- 2
Good afternoon,
I have been working on a LOMR for a small tributary due to (2) new culverts and the physical change in the basin. I managed to produce the duplicate effective, corrected effective, and new existing conditions plans just fine. At my first attempt at a Floodway Analysis using the encroachment tools on the new existing conditions information, I have so far been unsuccessful.
My approach is as follows: Using the 100-year storm flows in the steady flow data as the "base profile" I duplicated these flows and labeled it Floodway (so that I could use the encroachment tool). When I begin the encroachment analysis, I choose Floodway as my profile and method 4 with a W.S. increase of 1.0 feet.
This is where the problems arise. Do I then apply this to just the most downstream x/section as a start or every section on the tributary all at once? It seems when I try the approach I get values both well above 1.0 feet and others less than 0, not to mention the downstream x/section W.S. not increasing at all. I have the intention of getting this information close and then fine tuning with Method 1 and actual x/section station adjustments.
The HEC manual tends to lead me this far and then suggests "Good Luck." This could certainly be a beginners issue and an easy overlook but any advice and help would be greatly appreciated, I have some HEC experience but by no means would be an expert.
Thank you,
RC
I have been working on a LOMR for a small tributary due to (2) new culverts and the physical change in the basin. I managed to produce the duplicate effective, corrected effective, and new existing conditions plans just fine. At my first attempt at a Floodway Analysis using the encroachment tools on the new existing conditions information, I have so far been unsuccessful.
My approach is as follows: Using the 100-year storm flows in the steady flow data as the "base profile" I duplicated these flows and labeled it Floodway (so that I could use the encroachment tool). When I begin the encroachment analysis, I choose Floodway as my profile and method 4 with a W.S. increase of 1.0 feet.
This is where the problems arise. Do I then apply this to just the most downstream x/section as a start or every section on the tributary all at once? It seems when I try the approach I get values both well above 1.0 feet and others less than 0, not to mention the downstream x/section W.S. not increasing at all. I have the intention of getting this information close and then fine tuning with Method 1 and actual x/section station adjustments.
The HEC manual tends to lead me this far and then suggests "Good Luck." This could certainly be a beginners issue and an easy overlook but any advice and help would be greatly appreciated, I have some HEC experience but by no means would be an expert.
Thank you,
RC