Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Hello everyone, Me and my other tw

Status
Not open for further replies.

eXCELman

Structural
Jan 29, 2003
5
Hello everyone,
Me and my other two colleage designed a jetty structure having 2.5 km long. Structure was composed of a combination of 2 ( battered only in transverse direction at some locations) piles connected with a RC cap beam. Longitudinally the structure is connected with 2 I girders and CIP slab on top of them ( used for access road) and oil pipe line itself.
Piles are , at max. up to 60 m in length and they are partially in air then sea water then in sand , then in clay and touching the bed rock. We had to define whole structure in our model simply because the oil pipeline was continuous almost 750 meter long and every 750 meter there was an "S" in the pipe line. We performed response spectrum analysis using Maximum credible earthquake parameters.
Since we have got some excessive pile end forces (in tension ) at some locations , piles had to be anchored to the bed rock. For this purpose, some rock anchors are designed to take care of this force. As you know this rock anchor construction at a 60 meter deep is a quite difficult task to be performed for contractor.
For the seismic effects, we made use of reduction factors only for moments.
Indeed in seismic actions, (if the ends of piles not anchored to the bed rock) some slippage will be occurring b/w piles and the surrounding soil (clay and sand) and this will cause dissipation of seismic energy by frictional forces around the piles. Eventually this effect will reduce seismic forces and also axial tensile forces.Bu this effect can not be modelled quiet precisely in any Structural analysis program.

What reasonable reduction factor can we assume to reduce our tensile forces at the tip of piles? or Should we make the analysis using different techniques ( such as time history analysis or push over analysis )

Is there anyone who might have faced such a problem before ?

Comments will be highly appreciated.

Thanks to all.













 
Replies continue below

Recommended for you

It is very common to see seismic conditions govern the design of piles. You always end up with tremendous tension forces which oblige you to increase the length of your piles.
When it comes to look at the costs of constructing what has been designed, people always agree on some kind of reduction factors as found in all building codes of the world!
One thing, which I never tried but seems interesting, is the spin fin pile which has its tension capacity improved through fins.
See or contact a_christopherson@pnd-anc.com and good luck
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor