Asisraja D
Mechanical
- Jan 3, 2024
- 150
Hi professionals
We have purchased a steam boiler with capacity of 400 kg/hr at maximum operating pressure of 10 kg/cm2 and now we have planned to install a pressure reduction station. i will add some information below for better understanding.
1) Steam outlet nozzle size : 1"
2) Main steam line header size : 3"
3) PRS Station nozzles size : 1.5" X 2"
As the vendor suggest us to go for PRS station from 10 kg/cm2 to 3-4 Kg/cm2 for the header.
he just asked me a few questions to conclude this those are just
*how many branches you have planned for ?
*how much pressure you expect at the equipment side ?
* and he roughly says at 1" line you could have get 150 - 160 kg/hr steam flow rate.
my answer to that question is
we have planned for taking one secondary header (2") from the main header (3") then we planned for 6 branches at (1") nozzle.
we need 2 kg/cm2 at equipment side. (reactor jacket side)
can anyone please explain me a bit how exactly he could decide the factors here ?
i have attached the vendor quote and GA drawing of the boiler.
i need to some explanation for the conclusion made by him.
if anyone have few basics to make be clear on this please send me your valuable comments on this.
Thank you.
We have purchased a steam boiler with capacity of 400 kg/hr at maximum operating pressure of 10 kg/cm2 and now we have planned to install a pressure reduction station. i will add some information below for better understanding.
1) Steam outlet nozzle size : 1"
2) Main steam line header size : 3"
3) PRS Station nozzles size : 1.5" X 2"
As the vendor suggest us to go for PRS station from 10 kg/cm2 to 3-4 Kg/cm2 for the header.
he just asked me a few questions to conclude this those are just
*how many branches you have planned for ?
*how much pressure you expect at the equipment side ?
* and he roughly says at 1" line you could have get 150 - 160 kg/hr steam flow rate.
my answer to that question is
we have planned for taking one secondary header (2") from the main header (3") then we planned for 6 branches at (1") nozzle.
we need 2 kg/cm2 at equipment side. (reactor jacket side)
can anyone please explain me a bit how exactly he could decide the factors here ?
i have attached the vendor quote and GA drawing of the boiler.
i need to some explanation for the conclusion made by him.
if anyone have few basics to make be clear on this please send me your valuable comments on this.
Thank you.