Hey Experts,
Can any one tell me why we need to flush grind the reinforcement of weld when some attachment was coming on it?
Is it mandatory to do so?
ASME Sec VIII Div.1 UG-82 tells us toground flush the welds prior to fitment of an attachment.
If it is a spot Radiography joint is it mandatory to take the spot under the covered portion of weld?
Can any one tell me why we need to flush grind the reinforcement of weld when some attachment was coming on it?
Is it mandatory to do so?
ASME Sec VIII Div.1 UG-82 tells us toground flush the welds prior to fitment of an attachment.
If it is a spot Radiography joint is it mandatory to take the spot under the covered portion of weld?