LincolnPE
Civil/Environmental
- Mar 12, 2011
- 203
I work in a region where the storm sewer pipe system is initially sized for the Minor Storm event (2yr or 5yr depending on municipality). In the Major Storm event (100yr here) streets are allowed to have a depth above the gutter flowline of 12" in order to convey the major event as an open channel on top of the street (as long as all bldg lowest openings are 1 foot above 100yr WSEL,etc.). If that street capacity is still not enough during the Major Storm, the storm sewer would then be upsized to provide the additional required capacity.
The effects of the Major Storm on the storm sewer need to be shown. Some reviewers are mandating that the 100yr HGL is required to be 12" below flowline at the inlets. How can this ever be if the equilibrated 100 yr water suface elevation (WSEL) in a balanced design for the Minor and Major storms is one foot above gutter flowline?
The reviewers say to put what is going into the storm sewer from the inlet during the major storm (so that would be using the 1 foot of head above the gutter), and upsize the pipes if needed to keep this captured flow "HGL" 12" under the gutter flowline. Then analyze the system to ensure this "100yr captured HGL" is below manhole covers, etc.
The problem I see is that this is not the true HGL (static pressure) at the inlet location, that should be used to subsequently analyze the system. The true HGL and static pressure for the equilibrated 100 yr condition is always going to be relavent to the WSEL that is 12" above the gutter flowline.
The HGL that the reviewer would like to use to analyze the system is really missing 2 feet of head (1' below ground + 1 foot above ground)at these gutter inlet locations. This under estimates the true HGL for the subsequent system analysis.
Any thoughts?
The effects of the Major Storm on the storm sewer need to be shown. Some reviewers are mandating that the 100yr HGL is required to be 12" below flowline at the inlets. How can this ever be if the equilibrated 100 yr water suface elevation (WSEL) in a balanced design for the Minor and Major storms is one foot above gutter flowline?
The reviewers say to put what is going into the storm sewer from the inlet during the major storm (so that would be using the 1 foot of head above the gutter), and upsize the pipes if needed to keep this captured flow "HGL" 12" under the gutter flowline. Then analyze the system to ensure this "100yr captured HGL" is below manhole covers, etc.
The problem I see is that this is not the true HGL (static pressure) at the inlet location, that should be used to subsequently analyze the system. The true HGL and static pressure for the equilibrated 100 yr condition is always going to be relavent to the WSEL that is 12" above the gutter flowline.
The HGL that the reviewer would like to use to analyze the system is really missing 2 feet of head (1' below ground + 1 foot above ground)at these gutter inlet locations. This under estimates the true HGL for the subsequent system analysis.
Any thoughts?