Wrajeev
Electrical
- Oct 22, 2016
- 1
Hi,
About: Client wants Hi-pot Test on 114km - 138kV Transmission Line
Scenario: Transmission Feeder 1 live
Transmission Feeder 2 new (for testing)
Both Feeders on the same transmission line towers
Equipment: Biddle 70kVDC hi-pot tester
We were trying to perform the test but when we tried to connect the equipment, a strong discharge came from the new feeder line
Now, my question is it :
1. will the induced voltage be safe enough for the equipment if we did cut the new feeder line into 4 parts of 3 - 30km and 1 - 24km lines?
2. doable to perform hi-pot test on the new feeder line?
About: Client wants Hi-pot Test on 114km - 138kV Transmission Line
Scenario: Transmission Feeder 1 live
Transmission Feeder 2 new (for testing)
Both Feeders on the same transmission line towers
Equipment: Biddle 70kVDC hi-pot tester
We were trying to perform the test but when we tried to connect the equipment, a strong discharge came from the new feeder line
Now, my question is it :
1. will the induced voltage be safe enough for the equipment if we did cut the new feeder line into 4 parts of 3 - 30km and 1 - 24km lines?
2. doable to perform hi-pot test on the new feeder line?