Daryl1126
Mechanical
- Apr 26, 2004
- 2
Currently working on a renovation to a 40-story building which has a low and high zones for the HVAC hydronic piping. The client rep would like to install a single zone. Does anyone have experience with this type of zoning? We prefer to maintain the existing zoning.