Morquea
Electrical
- Feb 20, 2007
- 37
Hi
Question : Does a volatage regulator for 69kV line can could be used for a 120kV and vice versa? Does a auto-regulator on a line supplying 10MW would be affected and/or need to be change if we rise to 20MW.
Link about high-voltage regulators would be appreciated.
Project : Mining site developpement
Context : The utility had provides options for to supply power for a mining site in developpment. The total expected load is 20MW. They showed an option for 69kV wich was rejected and a option for 120kV wich was prefered.
However, environmental impact studies still need to be conduct before autorizing the use of 120kV. In the mean time, the utility offer to supply with 69kV on a line built for 120kV and they told use that they will use auto-regulator to cope with voltage drop. We should during that period build the temporary construction complex needed the develop the mining site. The power needed for this phase is 10 MW.
Once the normal mining operations begin, the utility should be able to provide the 120kV for a 20MW loads.
Finally, I'v been asked if the distributor would have to change is regulator to supply at 120kV and if we could stay at 69kV instead once the full 20MW is in operation.
I'm lacking knowledge to give a proper answer. So I told my coworker to simply ask the utility guys about it.
However, I would like to know more about high voltag-regulators and I don't have success with google
Thanks
Danny Garant, ing.jr
Groupe Stavibel Inc.
Question : Does a volatage regulator for 69kV line can could be used for a 120kV and vice versa? Does a auto-regulator on a line supplying 10MW would be affected and/or need to be change if we rise to 20MW.
Link about high-voltage regulators would be appreciated.
Project : Mining site developpement
Context : The utility had provides options for to supply power for a mining site in developpment. The total expected load is 20MW. They showed an option for 69kV wich was rejected and a option for 120kV wich was prefered.
However, environmental impact studies still need to be conduct before autorizing the use of 120kV. In the mean time, the utility offer to supply with 69kV on a line built for 120kV and they told use that they will use auto-regulator to cope with voltage drop. We should during that period build the temporary construction complex needed the develop the mining site. The power needed for this phase is 10 MW.
Once the normal mining operations begin, the utility should be able to provide the 120kV for a 20MW loads.
Finally, I'v been asked if the distributor would have to change is regulator to supply at 120kV and if we could stay at 69kV instead once the full 20MW is in operation.
I'm lacking knowledge to give a proper answer. So I told my coworker to simply ask the utility guys about it.
However, I would like to know more about high voltag-regulators and I don't have success with google
Thanks
Danny Garant, ing.jr
Groupe Stavibel Inc.