Are you asking how long a pump test typically takes? If we were rocking and rolling, we could get finished in about an hour for a smaller pump...fewer hoses. Most contractors and test companies have a 4 hour minimum charge which allows for travel time. So, if you looking for costs, figure 2 men at 4 hours. Your local testing company can tell you what the hourly rate is?
If this is an acceptance test, it is a minimum 1-hour test. And during the test I seem to recall it requires 6 manual and 4 automatic starts. One of those test must be under a full pump demand condition.
If your driver is electric and was required to be connected to a standby power source, an additional load test of the pump while the generator is running is also required.
We had some things come through that put a hold on the move for awhile. Still a goal, just going to get delayed. I am going to be dealing with a couple of Phoenix summers still :-(