rrowe1
Civil/Environmental
- Feb 13, 2008
- 5
I have 3 tributary areas delineated for use in TR-20. A flows into B. B flows into C. Ponding occurs in C because of a restrictive culvert. Is it accurate enough to ADDHYD A and B, then ADDHYD A+B and C, then route the final ADDHYD through a RESVOR created by the culvert? Or should I route the runoff from A through a REACH in B, then route the runoff from A through a REACH in C and route the runoff from B through a REACH in C to the culvert then route the 3 seperate hydrographs through a RESVOR created by the culvert? Thank you for your help.