James7443
Mechanical
- Jul 11, 2014
- 23
I currently have a system in place in which drawings are controlled either at an engineering level or at a production approved level.
When drawings are still in the engineering phase they can be update whenever needed without a formal approval signoff process. These drawings have an X# revision and are not available for production or purchasing use.
Production level drawings have gone thru a formal ECO system, to change their status from engineering to production approved, and have been given letter revision levels. The letter revision and the ECO number listed in the approval column of the revision table indicate that it is a production level print. This ECO system requires signature approvals from QA, Production, and Purchasing in addition to Engineering and Engineering Manager.
I am now getting some push in which some people in engineering don't like the ECO system to release prints to production. Instead they want to change the drawings from engineering level to production approved by eliminating the ECO, and the approval signatures from any department outside of design engineering. Approval would be done by two signatures in the title block and a signature in the revision table. This would eliminate Purchasing, QA, Production, and any other areas that currently review new drawings for production.
I am not sure what the exact driving for force is for this push to change. First it was time frame required for approval. After I proved that wrong, it was that other departments don’t provide any additional value on first release’s to production. When I provided a series of rejections by departments outside of engineering for errors or missing information, the reason changed again.
It should also be noted that if the system changes there will be two different way in which the revision table displays information indicating production approved drawings.
Sorry for the long message. Just wondering what other are doing and their thoughts.
When drawings are still in the engineering phase they can be update whenever needed without a formal approval signoff process. These drawings have an X# revision and are not available for production or purchasing use.
Production level drawings have gone thru a formal ECO system, to change their status from engineering to production approved, and have been given letter revision levels. The letter revision and the ECO number listed in the approval column of the revision table indicate that it is a production level print. This ECO system requires signature approvals from QA, Production, and Purchasing in addition to Engineering and Engineering Manager.
I am now getting some push in which some people in engineering don't like the ECO system to release prints to production. Instead they want to change the drawings from engineering level to production approved by eliminating the ECO, and the approval signatures from any department outside of design engineering. Approval would be done by two signatures in the title block and a signature in the revision table. This would eliminate Purchasing, QA, Production, and any other areas that currently review new drawings for production.
I am not sure what the exact driving for force is for this push to change. First it was time frame required for approval. After I proved that wrong, it was that other departments don’t provide any additional value on first release’s to production. When I provided a series of rejections by departments outside of engineering for errors or missing information, the reason changed again.
It should also be noted that if the system changes there will be two different way in which the revision table displays information indicating production approved drawings.
Sorry for the long message. Just wondering what other are doing and their thoughts.