Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

How much time to design ?

Status
Not open for further replies.

kurtz

Mechanical
Sep 10, 2016
34
How much time do You usually have to design:
-simple pressure vessel (about 10 nozzles)
-simple heat exchanger ((about 10 nozzles)
calculations + drawings

Two weeks, three weeks or more?
 
Replies continue below

Recommended for you

what is simple?
process data will largely dictate the design duration, along with codes, specifications, and other project specific requirements.
a 665-psig, 120-F, 3-phase separator took 6 months from RFP to complete the design.

more data will provide a better response.
 
If our engineering department is quiet (not bogged down with many other vessels), we have all of the necessary information, and it is a truly simple piece of equipment, we can normally complete calculations and drawings in as quickly as:
[ul]
[li]Simple pressure vessel: 3-4 days[/li]
[li]Simple heat exchanger: 1 week[/li]
[/ul]

That said, it's very rare that this is the case. Often information is missing, a request is made for some unusual design feature, or the order comes in alongside 5 or more other pressure vessels. In which case, similar to pmover's experience, this can extend out to 2-weeks, 4-weeks, ..., 6-months.

It often amazes me how purchase orders are sometimes placed when the buyer has so little information available. What are they buying?! Then I spend over a month dragging the information out of the customer before I can complete the design.
 
Two other major factors- the degree of software support available, and the amount of previous experience with similar items.
So, a simple vessel per your note, maybe a week for one person, assuming design is per vessel software, drawing is by AutoCAD, and that previous details are available to cut-n-paste.
If you had to work through the design by hand, and then drew the first vessel like that you ever drew, then more like 3-4 weeks.
If you're also learning the code as you go along, even longer.
In real life it's "Do this ASAP! But first, do this other thing...And this other thing...oh, here's a hot item, fit it in front of there..."
 
JStephen said:
In real life it's "Do this ASAP! But first, do this other thing...And this other thing...oh, here's a hot item, fit it in front of there..."

Couldn't have said it better!

That's when I call a meeting with the sales team, lay in front of them all of the to-do items that have been thrown on my desk in the last week, and ask them to set priorities. Then I sit back and watch the fireworks. [swords]
 
Assuming you had just ONE project to work on: anywhere between 1 day and 1 year.

What are the design considerations: is it a Code vessel? What code? ASME, PED, MOM?
What is a 'simple pressure vessel'?
Are you worried about just ASME calcs? Does the customer want wind/seismic FEA? What if they ask for environmental impact analysis?
What if they want it painted with a paint / rust preventative that's illegal to use in the country of manufacture?

The point being: A 'simple pressure vessel' to one person (sales team) might not be the same thing to the engineer.

What happens when you spend a month trying to get it to submit to the broken web-portal that they REQUIRE you to interface with....then they take 2 months to get back with customer approval on comments that they demand you resolve instantly?

It almost sounds like a question that a sales manager would ask on this form to try and paint his engineering team as lazy/taking too much time.
"Well, OTHER engineering teams could do it in X days..."

Be careful when answering questions like this to sales/project managers...they tend to have amnesia about all the details and only worry about the time quoted BEFORE they give you all the customer specifications.

Don't forget JStephen's comment: ...do this as your #1 priority...but this OTHER project should be a higher #1 priority...
 
As others have said, it can vary greatly, but, for a TEMA type shell & tube exchanger:

1) Read contract, perform mechanical calculations, prepare ACAD layout & Outline drawing:
Low End: 16 hrs, High End: 40 hrs

2) Make & check shop drawings
Low End: 40 hrs, High End: 120 hrs.

3) Address customer and internal questions, conference calls, NCR's & general crisis management:
Low End: 10 hrs, High End: Sky's the limit :)

Regards,

Mike


The problem with sloppy work is that the supply FAR EXCEEDS the demand
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor