How to move the whole schedule? 4

Status
Not open for further replies.

oxana

Mechanical
Jan 16, 2002
23
Hi,

Is it possible (and if yes - how?) to move the whole schedule in MS Project without changing durations of any tasks. Let's say we create a project that would end on December 15 and it would take 6 weeks to complete all of its tasks (often linked). Now we want to move the completion date to December 1, moving the start date also as well as all the tasks at once. Can this be done?

Thank you,
Oxana
 
Replies continue below

Recommended for you

Sure, but only for the linked tasks.

You can change the project start date in the menu selection

Project|Project Information

TTFN
 
The Project start date is greyed-out and cannot be changed. I can change the start date of the first task but that simply makes the project longer; it does not move the whole project. What am I missing?
 
It seems to me that you have a constraint in the end date of the last activity, or in one task of the critical path, that is not allowing the last task to come. Check for constraints.

Also you say that is greyed out?... like if it were only showing the baseline... Check for constraints and if that doesn't work, let me see the file.

SANTO.
 
In the menu Project/Project Information check if you didn't shedule your project by end date. Then the start date is grayed out and you must set your end date of the project to your new date
 
There is little known macro in Project that will move all activities wheter linked or not.

i.e you have project that started on 01/01/04 and there is a repeat starting 01/01/05.

to get there:

Go to "view" - "Toolbars" - "Analysis"

There will now be a new tool bar.

Press Adjust dates.

And the rest is straight foreward.

You can change the date backward


Cheers

Blooda
 