streng9999
Structural
- Oct 11, 2023
- 5
Hello.
I am connecting a HSS to a 6" concrete slab using mechanical anchors.
My initial design approach was to resolve the entire moment demand into a force couple on the two anchors going into the slab mid-depth and just use the distance between the anchors and the bottom of the connection plate (d) as the moment arm but I'm not getting close to the required capacity. The tension demand is ~20 kips per anchor using that approach.
I'm trying to add additional anchors connected to the bottom of the slab but unsure as to how the overall connection would work as the concrete failure planes for the two sets of anchors would overlap.
I'm looking for different connection ideas or approaches if anyone has experience with this.
I am connecting a HSS to a 6" concrete slab using mechanical anchors.
My initial design approach was to resolve the entire moment demand into a force couple on the two anchors going into the slab mid-depth and just use the distance between the anchors and the bottom of the connection plate (d) as the moment arm but I'm not getting close to the required capacity. The tension demand is ~20 kips per anchor using that approach.
I'm trying to add additional anchors connected to the bottom of the slab but unsure as to how the overall connection would work as the concrete failure planes for the two sets of anchors would overlap.
I'm looking for different connection ideas or approaches if anyone has experience with this.