hidalgoe
Electrical
- Jan 14, 2002
- 42
Hello:
Our main substation consists of two 69kV/12.47kV, 20mVA xformers with a switchgear lineup for each transformer.
A NO tie breaker interconnects both lineups. Recently two solid state undervoltage relays were added to the system to initiate transfer/retransfer.
Soon we will have a basewide shutdown to perform much needed PM on various HV substations, pad mtd switches, SF6 CBs and OCBs, etc. At this point we are going to test the transfer scheme at our Main Sub. Our dilema is whether to test the scheme simulating an undervoltage condition by shutting of the PT reference voltage or by opening a primary 69kV airbreak switch to either transformer.
The only load on the transformer will be supply and exhaust fans. Some folks are worried that opening the switch will somehow harm the system insulation.
Your response will be kindly appreciated.
Hidalgoe@FAA Tech Center