lhwingking
Petroleum
- Feb 12, 2013
- 39
I have a piping system that is above ground in which Hydrotest is going to be performed. At a particular location it goes underground and comes above ground after a certain span. In this location where it goes underground, it makes a low point that calls for a hydrostatic drain. But it is going to be fully burried. How will the the drain valve in this underground location be operated? If I do not provide a drain valve here, how will the water be drained after hydrotest?