The geotechnical report for the drilled shafts (approx 3'-6" dia) I'm working on says to add hydrostatic pressure when below the groundwater table. I'm hoping for guidance on how this load should be applied. As far as I understand, the 62.4 pcf value should be multiplied by the depth of the pier below the GWT and the resulting value applied as a psf uplift load to the end area of the pier with a factor of 1.6.
Am I missing anything there?
Am I missing anything there?