Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Hydrotest prior of NDT and PWHT

Status
Not open for further replies.

Eduardo1982

Mechanical
Oct 31, 2014
65
Hey guys I hope ervtybody here is fine.
I wish to know yuor ideas in regards of the next topic. As it is stipulated in several docs and codes PWHT and NDT must be done before of any test pressure on lines. In many systems, like steam lines to turbines or boilers, the chemical cleaning and steam blowing Will be done after test pressure. However, as normal practises, some valves are installed after chemical cleaning & steam blowing process and welding Works (with NDT & PWHT) must be performed as "Golden joints". The point is that.. what could be the risk if instead to perform NDT & PWHT on time before of hydrotest, I decide to perform some PWHT & NDT after chemical cleaning? If I believe that my welders are skyll enough so probably I won´t have any problem with the soundness of the welds…. or is there any problem related to mechanical properties on the pipe that I could see only with hydrotest?
 
Replies continue below

Recommended for you

A golden joint is with a exception to hydrotest.. so for the specific valve joints identified already as golden joints, what you intend to propose is already being done.. need more elaboration in your question if I couldn't get it right.
 
If you are the owner, why bother for a hydro-test?
Unless you are not the owner....

DHURJATI SEN
Kolkata, India

 
IMO you should perform NDT & PWHT on time before of hydrotest. After all welding is complected than you steam blow and chemical clean if it is a boiler than you finally make the hidrotest with demi water.

luis
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor