DusanAust
Mechanical
- Dec 28, 2003
- 2
Is anyone aware of a Code requirement to hydrotest stainless steel instrument tubing in gas plants (the compression jointed type)
I am familiar with the normal procedure for hydrotesting pipework prior to commissioning, however the stainless steel instrument tubing appears to not normally be tested. I've reviewed a couple of the piping standards and they appear to neither specifically exclude the tubing or include it. Any help or experiences on this topic would be most appreciated.
Cheers
I am familiar with the normal procedure for hydrotesting pipework prior to commissioning, however the stainless steel instrument tubing appears to not normally be tested. I've reviewed a couple of the piping standards and they appear to neither specifically exclude the tubing or include it. Any help or experiences on this topic would be most appreciated.
Cheers