Thank you for the responses.
I am using piers instead of a stem wall due to the fact that the soil is quite expansive.I know l could use a standard pier and beam with void boxes but since lm doing this myself it would be much easier to put I-beams on top of piers and frame it up from there.I plan to have the piers drilled to ten feet,16" in diameter. A slab would be impractical due to the slope of the area. And I guess garage is not the correct word- more of a work shop. No car will need to be supported. Just the usual, tools and such.
So my plan was to put concrete piers (using sonotubes as needed) around the perimeter every ten feet, bolt an l-beam on top of the piers and frame the floor in much the same way a house is built.
l have observed that standard traffic light poles are bolted to concrete piers with four bolts. Would this be the best way to secure the beams? I have already built 1/2 inch by 8"x8" plates with three piece of number four rebar, about one foot long, welded to the bottom so that they will project down into the concrete. I had planned to simply place these into the concrete before it cures so that the plate just rest on top of the pier.(Of course l have also fabricated #4 rebar cages for each pier.) But now lm not sure if the plates are the right way to go. Will they transfer the load without cracking the pier? (I don't know if its relevant but the concrete will need to be pumped.)
Thanks again.