Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SDETERS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ice chiller start-up & commissioning

Status
Not open for further replies.

hvacman

Mechanical
Feb 23, 2001
5
I'm the PM for a mechanical project including (2) 150 ton centrif. chillers & (1)ice chiller (BAC). The target date to commission CHW system is end of March 03, however my concern is that at this time there may not be substansial load to properly commission. The centrif. chiller manuf. recommends minimum 75-100 tons load minimun. The BAC ice chiller is scheduled for ice build during winter months. Does anyone have any recommendations including potential risks to prep for including advice on partial commissioning of this type system?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor