sparkview
Electrical
- Nov 12, 2015
- 59
Dear all,
Consider the configuration below. The protection scheme consists of a RET615 protection relay with included overcurrent and differential protection for the Transformer. The CT's on the secondary side of the Transformer is still pending to be installed, however, there is not much space to install CT's at the switchgear in Substation 2 (location 2). Would there be an issue installing the CT's at 'location 1' near the Transformer secondary side? Also, any pointers with regards to IEEE, NEC reference is greatly appreciated.
Consider the configuration below. The protection scheme consists of a RET615 protection relay with included overcurrent and differential protection for the Transformer. The CT's on the secondary side of the Transformer is still pending to be installed, however, there is not much space to install CT's at the switchgear in Substation 2 (location 2). Would there be an issue installing the CT's at 'location 1' near the Transformer secondary side? Also, any pointers with regards to IEEE, NEC reference is greatly appreciated.