To ACtrafficengr
Yes, but I better add some extra thoughts.
On several occasions, we have had a major highway lowered in the same location as a major water main (up to DN 1,400) but this lowering would only be for a year or two, then the normal cover of 750 mm would be restored. So it seemed a very expensive exercise to lower the pipe & then put an extra soil cover back. The slab can be cut up & removed, if required at any time.
I have found that all you have to do is excavate a 150 mm depth in the soil, place N12-150EW in the excavation, then place a 150 mm layer of concrete. If you do the sums it is usally OK for all highway loadings even with a small cover.
Place 25 mm polystyrene on the bottom of the slab immediately over the pipe to allow for any traffic loading deformation to take place there. This is a bit probermatical because polystyrene does have a modulus & some loading will be transmitted thru the material - however, it always seemed to be a good idea to me - I'm not quite happy with long term effects of polyurethane on the environement.
Make the slab slope slightly away from the pipe on each side. I do this just in case there is some settlement in the cover soil. The slope means that any deformation will gradually be less, the closer the traffic will come to the slab over the pipe. I believe these relief slabs have been used as approach slabs on bridge abutments for the same reason.
As you can see, the sums are very simple, formwork is practically nil, very little steel & concrete, with the result a very simple design.
I design the slab as simply supported over a span equal to the diameter of the pipe but this is not strictly correct. Some of the support load (on both ends of the slab) must go vertically down & some of this load must go to the sideways support of the pipe. Remember though, the greatest deflection problem in an empty pipe (once in a blue moon, but still a design condition) is a vertical deflection on top of the pipe & an empty pipe design always assumes a design zone of D (pipe diameter) high & 2.5 D on either side of the pipe. The slightly extra side load will in actual fact, help support the empty pipe from the vertical deflection.
Another method of taking a load, is to place concrete over the top half of the pipe &, in effect, make a pipe arch over the pipe. In this way, the vertical load is taken by arch action to both sides of the pipe BUT as a vertical load with very little influence to the structural action of the pipe. Of course, use a polystyrene layer over the pipe.
BarryEng