Hello, Does anyone know any formulas that help in evaluating the potential of driving proccess of piles on adjacent buried steel pipelines. Pipelines are from 2 to 4 inches steel pipelines buried at 3 to 5 ft in very soft soil. The piling of the buliding are made of woood (8 to 12 inches)and they are far around 15 to 20 ft from the pipeline. I am using Attwell and Framer (1973) formula that requires pile energy per blow, empirical soil parameter, and source distance, to evaluate the Peak Particle Velocity (PPV). I used this formula for building before in combination with monitoring program.
But I cannot find in the codes ASME or Canadin the permissible value of PPV for undergraound utilitits
Any help or refernce to helpful materials concerning this subject is appreciated. Much appreciated.
But I cannot find in the codes ASME or Canadin the permissible value of PPV for undergraound utilitits
Any help or refernce to helpful materials concerning this subject is appreciated. Much appreciated.