Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Installing 24-in diameter pipie piles using Pre-drilling to avoid noise and vibration

Status
Not open for further replies.

geoneeds

Geotechnical
Nov 21, 2009
2
For a bridge foundation, we have 24" dia open end pipe piles. I wrote the foundation report (FR), and in FR, center relief drilling was recommended if hard driving is encountered. But the contractor (for construction) suggests installing 24-in diameter pipe piles using Pre-drilling to avoid noise and vibration. If we do that we will lose a lot of capacity by side resistance/skin friction. I have seen/heard that many precast concrete piles are driven in pre-drilled holes due to hard driving (whereas concrete pile are displacement piles), but I have not seen/heard open end pipe piles(24” open end pipe piles are non-displacement piles)installed in pre-drilled holes.I am wondering whether I should change the design to drilled shaft. The soil is mostly sandy with few gravels. The ground water is deep.Thanks in advance for your suggestions.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor