rajisha2002
Mechanical
- Jan 10, 2002
- 4
hi guys'
we are new at installing directly buried (in earth) chilled water district cooling piping .Our application is pre insulated black steel piping with welded joints.We had carried out stress analysis through a certified consultant ,software used was Ceasar-II .Result was cancellation of the design intent of thrust blocks & flexible joints on piping while introduction of concrete anchor points (mass concrete)at very few locations(at entry point of piping to buildings),further the piping was allowed to move with polystyrene wraps at changes in direction of pipes while remaining buried.
Is this feasible in normal practices?
The design consulant for the piping is very skeptical of the proposal and objected to the design of the concrete anchor blocks .
Please help ,if we have cerified concrete anchor block design procedures for buried steel piping.
Working Pressure in piping is very minimal 4.6 bar ,application is in the middle east area.Piping is buried with normal dune sand over it.
we are new at installing directly buried (in earth) chilled water district cooling piping .Our application is pre insulated black steel piping with welded joints.We had carried out stress analysis through a certified consultant ,software used was Ceasar-II .Result was cancellation of the design intent of thrust blocks & flexible joints on piping while introduction of concrete anchor points (mass concrete)at very few locations(at entry point of piping to buildings),further the piping was allowed to move with polystyrene wraps at changes in direction of pipes while remaining buried.
Is this feasible in normal practices?
The design consulant for the piping is very skeptical of the proposal and objected to the design of the concrete anchor blocks .
Please help ,if we have cerified concrete anchor block design procedures for buried steel piping.
Working Pressure in piping is very minimal 4.6 bar ,application is in the middle east area.Piping is buried with normal dune sand over it.