peterb1441
Geotechnical
- May 17, 2005
- 6
Does anyone have any experience of installing gabions and renomattresses in winter, in frozen ground, for riverbank erosion protection? I know the US Army COE does not permit this. In my opinion, preparation of the banks would be difficult, and maybe there would be uneven settlement in the spring thaw. I'm in a part of Russia where the winter is 7 months long, and where there are restrictions on working in or near rivers in the thaw period. I also have an inept contractor, whose previous mattress installations have been rejected my myself. Any responses would be appreciated