My questions are related to installation of Tower Trays :
1) Whats the procedure of installation of sieve trays in a tower . Are they installed afer fabrication of tower or during the facrication ?? The problem I am facing is that the diameter of the vessel is 800 mm and the height is 14560 mm . Is 800mm would be enough for a person to enter and install the trays b/c the delivery time of trays is taking long time then we have expected .
Thnkyou and Regards
1) Whats the procedure of installation of sieve trays in a tower . Are they installed afer fabrication of tower or during the facrication ?? The problem I am facing is that the diameter of the vessel is 800 mm and the height is 14560 mm . Is 800mm would be enough for a person to enter and install the trays b/c the delivery time of trays is taking long time then we have expected .