Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Internal line-up clamps

Status
Not open for further replies.

elylrc

Mechanical
Oct 7, 2010
20
The offshore pipelay contractor used a manual weld to weld a 12-inch barred tee to the pipe and then the ILUC to weld the next joint to the tee. The tee was made from half in pipe and the pups were made from 0.438-inch. The pipeline is 12 x 0.438. The contractor's reason for the manual weld vs using the ILUC was that the ILUC would not fit through the tee. The contractor of course is claiming extra time for making the manual weld. However, the difference in wall thickness is about 1/16-inch.

Does anyone know what wall thickness a 12-inch ILUC can accommodate without changing the factory settings? Or does anyone now why the manual weld was performed?
 
Replies continue below

Recommended for you

Can we pay him and get on with laying pipe.

Let your acquaintances be many, but your advisors one in a thousand’ ... Book of Ecclesiasticus
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor