ijlm
Civil/Environmental
- Oct 14, 2004
- 1
I have boring logs on a project which give SPT values and a classification chart for the N values. Some of the SPT values have two numbers, eg. 50/3. I understand this to mean it takes 50 blows for the split spoon to penetrate 3" - is this correct? (I am not a geotechnical engineer!) I also presume that this is very hard material (Yes?) but why would the blow count not continue until the foot penetration was achieved and report the resulting N value (blow vounts per foot)