Dear friends,
i have a span of 18m. (see image below).
The purlins are in a 1,5 distance carrying a load of 2,2kN/m each.
I analysed the system using my software. A HEA 400 seems to be enough. But...i am new, i would think more reasonable a IPE450-500, and would like your thoughts/suggestions.
Architects don't want a beam higher than 400mm for their reasons. Because there is not a lot of free height under the roof
i have a span of 18m. (see image below).
The purlins are in a 1,5 distance carrying a load of 2,2kN/m each.
I analysed the system using my software. A HEA 400 seems to be enough. But...i am new, i would think more reasonable a IPE450-500, and would like your thoughts/suggestions.
Architects don't want a beam higher than 400mm for their reasons. Because there is not a lot of free height under the roof