bdn2004
Electrical
- Jan 27, 2007
- 797
I'm on a project that is to replace a number of medium voltage cables to some motors. The motors operate at 4160V. The biggest motor is 500HP, 75Amps or so.
This is an emergency job. The existing cabling is #2/0, the engineering firm specified #2. It seems like they used the 1.25 rule per the NEC which doesn't apply to our situation.
They have the coordination study which I would assume they used to size this...but I'm telling our guy not to get something smaller that what was there - as its no sweat on us, but could if that's too small.
Is this being over cautious? This is at a power plant.
This is an emergency job. The existing cabling is #2/0, the engineering firm specified #2. It seems like they used the 1.25 rule per the NEC which doesn't apply to our situation.
They have the coordination study which I would assume they used to size this...but I'm telling our guy not to get something smaller that what was there - as its no sweat on us, but could if that's too small.
Is this being over cautious? This is at a power plant.