Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Jack-and-bore under-roadway crossing for 6"-10" pipe

Status
Not open for further replies.

Gaylon

Civil/Environmental
Aug 13, 2006
2
To install 8" water main under-crossing a roadway. If open-trenching is not allowed, is jack-and-bore the best/low-cost method to use? Versus, directional drilling? Are there any known problem areas to this approach? Any good references concerning this method?

 
Replies continue below

Recommended for you

Boring-drilling and jacking is a good method to use and is routinely done. Problem is depth of excavation needed to get the boring-jacking machine down low enough to push the pipe in below the minimum cover required for the pipe under the road. Soil suitable for boring and jacking is required. Rock would require tunneling.

Horizontal drilling is more dependent on pipe and soil conditions. Disadvantage when compared to horizontal boring is the stand-off distance needed to slowly curve the pipe down under the road, cross underneath, and curve it up on the other side, without overstressing the pipe in bending a radius too tight. I'm guessing you will need a radius of around 1000 feet, although I don't know the wall thickness of your pipe. Say 800 to 1400 ft radius might be average. So using that radius, you have to curve down, curve flat, then curve back up then curve horizontal again. You may have to get back away from the road several hundred feet to begin the drilling poing, use a heavier wall thickness pipe, and receive the pipe several hundred feet on the other side of the road. Large bolders that can deflect the boring head are a problem as well as sand that can collapse around the bored hole before the pipe is pulled through.

Going the Big Inch! [worm]
 
We have had some recent cave-ins in Michigan where the jack-and-bore contractor got ahead of themselves. Caused the shutdown of a major highway off-ramp in one case. Two of the cave-ins involves dry, poorly-graded sand soils.

Another thing to be aware of with both techniques is bolders. They can cause problems.
 
Jack and bore is the most common method. The only problem is that it is more expensive $300-400/ft than open cut. It is commonly requested when the pavement is relatively new or the traffic is heavy.

On a recent project, 6" diameter pipe was directionally drilled instead of jack and bore. When you get into the smaller diameters it is not economical to put the pipe in a casing. The casing pipe should be 6" larger on all sides or plus 12"
 
You will have to check with the roads authority if a casing is required. If there is a leak then washout can be a problem so sometimes casings are a requirement by the owner.

For directional drilling in most soil conditions bentonite or polymer is needed. This should hold the excavation open preventing the collapse of soil, including sand, before the pipe is pulled through.

I think directional drilling would be the more economical method for a 6-10" water main.
 
BigInch (Petroleum),

Most of the municipalities where I work require casing for water and sewer work.
 
I recently installed about 180 feet of 20" ductile iron water main via horizontal dir. drilling. Had to use special locking joints, but it was fairly cost effective at ~$250 per foot.
 
Gray and ductile cast iron pipes have been e.g. push inserted inside various types of casings e.g. installed by various boring, jacking, and tunneling means as well as larger existing pipelines for many decades. This has been described to some extent for many years with regard to "Highway and Railroad Crossings" in a section of ANSI/AWWA C600 as well as AWWA Manual M41. I agree with Mr. BigInch that boring, jacking, or tunneling with conventional casing pipe, and then placement of a carrier pipe (often from the common boring/jacking etc. pit) for watermain or sewer service, is probably still the most common approach.
There are however now available many styles of quite formidable strength ductile iron pipes that can also be installed by many different “trenchless” (or perhaps more accurately in many cases, “less trench”) means, e.g. as can be observed through the portal where same procedures are preferred and acceptable to authorities.
We have seen increasing numbers of these projects since the early 1990’s, with a marked increase in horizontal drilling projects with flexible, restrained joint ductile iron pipe since 1996. I would only further point out that with contemporary ductile iron joints/systems, the long piping assembly/layout area mentioned in some of this thread (as a disadvantage common to HDD with other types of pipes) is not necessary with ductile iron pipes, as the very rapid assembly of these contemporary joint structures does not require lengthy field welding and/or cooling periods, and thus also allows for quick insertion of individual pipes, e.g. in a relatively short “pipe insertion/assembly pit”, in “cartridge” loading fashion. In fact, in the first 6” (`150 mm) ductile iron project I saw installed by HDD in 1996, I think the pipe never even hit the ground after a pulling head was assembled onto the first plain end and dropped down to connect to the drill string behind the reamer, but thereafter the pipes were basically loaded from a stack on a flat bed truck that was parked next to the pipe insertion pit, which in turn was basically just a “trench box” for worker joint assembly safety that had been quickly dug/sunk into a rectangular trench with a backhoe that the contractor had drilled to/reamed from at desired pipe depth.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor