cvg
Civil/Environmental
- Dec 16, 1999
- 6,868
we are proposing to jack a gravity storm drain line between two large diameter gravity sanitary sewer lines (2 - 90 inch above and 1 - 84 inch below). Clearance is limited and invert of storm drain would be about 20 feet below the surface. The material is silty / clayey / sand and deeper than about 25 feet turns to silty gravels and cobbles. It appears that there is some cohesive material in the upper 20 feet.
I have several questions.
1. First option was to jack a 4'H x 8'W concrete box culvert. We have not had success locating a contractor who has jacked a box culvert - apparently has not been done in Arizona. Anyone have experience with jacking boxes?
2. Can an eliptical pipe be jacked without using a casing?
3. What methods are recommended for
a) stabilizing / shoring the jacking pits
b) stabilizing the excavation at the sheild
4. Would going underneath everything (in a siphon) pose any significant additional stress on the existing large sewer lines? Invert would be closer to 40 below surface and pipe would be probably 96 inch diameter.
I have several questions.
1. First option was to jack a 4'H x 8'W concrete box culvert. We have not had success locating a contractor who has jacked a box culvert - apparently has not been done in Arizona. Anyone have experience with jacking boxes?
2. Can an eliptical pipe be jacked without using a casing?
3. What methods are recommended for
a) stabilizing / shoring the jacking pits
b) stabilizing the excavation at the sheild
4. Would going underneath everything (in a siphon) pose any significant additional stress on the existing large sewer lines? Invert would be closer to 40 below surface and pipe would be probably 96 inch diameter.