Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

JAcking system on Floating Roof Tank

Status
Not open for further replies.

Syahar1975

Mechanical
Feb 3, 2011
224
Good morning Gents,

It is common for EFRT which is built by using conventional method (shell lifted by crane from shell course#1) that the floating roof is built in parallel with shell courses after completion bottom plate and shell course #1.

How about in jacking system ? I think we have to wait to build the floating roof till all shell are completed erected and welded.

I agree that jacking system will eliminate working at height. But in tank construction something that can be done in parallel will contribute significant effect in squeezing the overall schedule. Also we need a bigger crane to built the roof.

Is there any study that jacking system in overall (safety, schedule and cost) is better than conventional method ?

Your comments is highly appreciated.

Syah




 
Status
Not open for further replies.

Part and Inventory Search

Sponsor