avl58
Structural
- Sep 5, 2014
- 2
I am having a large ICF home built. It is an on grade slab with 36" footings and a 4" slab. The foundation was engineered.
Shortly after the pouring started rain came that lasted for nearly 6 hours, basically during the entire pour. Rain varied from heavy to light. Parts of the slab were covered but a lot of it was not. At one point one of the cement trucks got stuck in mud, so they brought in a pump to pump in the concrete from 120 feet from the road. So there was about a 45 minute gap between pours and also a slight change in concrete mixtures.
A lot of the surface did not look good so they added dry Portland cement and worked it in the with power trowler. Some of the corners are washed away and you can see rough stone. There is also a lot of color variation with some areas being completely white and others gray.
The contractor and concrete company are saying it is just cosmetic and are going to do a PSI check in 28 days.
What should we do? Is it enough to do the PSI test? Or, does the surface need to be removed and a few inches added onto it?
Shortly after the pouring started rain came that lasted for nearly 6 hours, basically during the entire pour. Rain varied from heavy to light. Parts of the slab were covered but a lot of it was not. At one point one of the cement trucks got stuck in mud, so they brought in a pump to pump in the concrete from 120 feet from the road. So there was about a 45 minute gap between pours and also a slight change in concrete mixtures.
A lot of the surface did not look good so they added dry Portland cement and worked it in the with power trowler. Some of the corners are washed away and you can see rough stone. There is also a lot of color variation with some areas being completely white and others gray.
The contractor and concrete company are saying it is just cosmetic and are going to do a PSI check in 28 days.
What should we do? Is it enough to do the PSI test? Or, does the surface need to be removed and a few inches added onto it?