rholder98
Structural
- Oct 5, 2005
- 158
I have to plan for a future clarifier to be built adjacent to the pump station and clarifier I am currently designing. That is, eventually, it will be two clarifiers with a pump station between, but only the one clarifier will be built in this contract. What's the best way to detail the foundation so that it can be expanded later? Could I leave rebar exposed--coated and protected--ready to receive the future basin mat? Is there a "soft" concrete that could be demo'd later? Or should I just let the next guy worry about it?