jechols
Structural
- Jan 21, 2004
- 109
thanks for responding to last question. same job as unsupported wwf. I have now discovered that the porous fill under the slab is only 2" to 2 1/2" on average and as thin as 1" to 0" is a several locations as well 4" in a few isolated areas. My concern is that this could lead to more cracking. An easy solution is to just decrease control joint spacing or should I insist that the contractor remove the wwf, vapor barrier, gravel and adjust sub-grade to the correct elevation. The second option would delay the job and make everyone generally unhappy. I just don't want to cause this much if the increased risk of cracking is small.