jmf
Mechanical
- Apr 19, 2001
- 5
I'm a mechanical engineer building a light-gauge steel framed house. Light-gauge steel beams and floor joists will be anchor-bolted to concrete filled (concrete) block (crawl space) foundation wall and interior piers. I need a level surface for the beams/joists. The blocks are level and piers/walls straight. However, concrete was not completely filled to the top of all blocks. Some walls/piers need an additional 1/2 inch to 2 inches of concrete to allow a level surface for beam/joist placement. I do not want beams/joists resting only upon the blocks.
Everyone asked (from concrete contractors to concrete product vendors to know-it-all neighbors) have recommended different products to fix the problem. I have not received the same answer twice (except leave-as-is).
I plan to (eventually) live in the house.
Thanks in advance for your opinion.
Everyone asked (from concrete contractors to concrete product vendors to know-it-all neighbors) have recommended different products to fix the problem. I have not received the same answer twice (except leave-as-is).
I plan to (eventually) live in the house.
Thanks in advance for your opinion.