mzafarnawaz

Civil/Environmental
Mar 1, 2011
1
i am going to work on high rise building ,as the columns i plan to use gird line to alignment but but i don't know how to alignment the
liftcore wall formwork......
i am going to use total station.
building hight is 50 stories.
 
Replies continue below

Recommended for you

set out the kickers for the core walls, once the kickers are concreted and the formwork is stood use the same co-ordinates you used for setting out the kickers to check the alignment of the top of the formwork and adjust using push-pull props bolted to the formwork and to the slab.
hope this helps.
 