ronishm
Specifier/Regulator
- May 23, 2007
- 1
Hello,
I'm working with SureTrack and have a full construction schedule. Related to the work, but seperate is a small schedule of extra work. I would like to link the two in the same schedule, but not have the critical path of the main schedule be affected by that of the extra work. Is there any way to show two schedules linked in the same page, but each with their own governing logic?
Thanks
I'm working with SureTrack and have a full construction schedule. Related to the work, but seperate is a small schedule of extra work. I would like to link the two in the same schedule, but not have the critical path of the main schedule be affected by that of the extra work. Is there any way to show two schedules linked in the same page, but each with their own governing logic?
Thanks