Hi...
I've just recently started using MS Project and i was really amazed by the appealing interface... but i have just discovered that i can't link 2 tasks with 2 or more relations... meaning that i can't for example link tasks no. 2 & 3 with both SS AND FF relations (i'd like to do that with lags included too)... i get a message that i can't do that... is there a way to get around this? I really would like to avoid Primavera...
Thanks in advance...
Ahmed Hassabu
I've just recently started using MS Project and i was really amazed by the appealing interface... but i have just discovered that i can't link 2 tasks with 2 or more relations... meaning that i can't for example link tasks no. 2 & 3 with both SS AND FF relations (i'd like to do that with lags included too)... i get a message that i can't do that... is there a way to get around this? I really would like to avoid Primavera...
Thanks in advance...
Ahmed Hassabu