vger
Electrical
- Feb 14, 2007
- 2
I'm an electrical engineer that's been given a supervisory role relating to a production change and associated construction.
We are getting a small hoist installed on a pre-engineered rig that can handle 4000lbs bags. It's a 4 post arrangement with 4"X4" feet that are to be lagged to the floor.
The engineering firm doing our construction work says 7" of reinforced concrete slab on grade will be more that sufficient. The new concrete floor replaces a previous slab that while slightly cracked had no issues.
So my questions are:
1. Is he right?
2. What are the engineering units for "strength" that I need to be concerned with? How are they defined and what typical values should I anticipate.
3. What testing should I expect to confirm that it is sufficient?
The firm is very reputable, but I would like to be more informed about the proposed slab as I don't know if they have done calculations or are just using a "rule of thumb" with a safety margin.
Thanks
We are getting a small hoist installed on a pre-engineered rig that can handle 4000lbs bags. It's a 4 post arrangement with 4"X4" feet that are to be lagged to the floor.
The engineering firm doing our construction work says 7" of reinforced concrete slab on grade will be more that sufficient. The new concrete floor replaces a previous slab that while slightly cracked had no issues.
So my questions are:
1. Is he right?
2. What are the engineering units for "strength" that I need to be concerned with? How are they defined and what typical values should I anticipate.
3. What testing should I expect to confirm that it is sufficient?
The firm is very reputable, but I would like to be more informed about the proposed slab as I don't know if they have done calculations or are just using a "rule of thumb" with a safety margin.
Thanks