mikeengurs
Electrical
- Oct 18, 2011
- 49
I'm planning to add motor loads to an MCC fed from a 4160v swicthgear. For that, I'd like to to run a load flow and short circuit analysis to see if existing system can handle it. Both existing swicthgear and MCC have existing motor loads on them. My question is, if the plant gives me short circuit and other information at my tie point, can I use the MCC bus as my swing bus in SKM, and just model the added load, or I need to model everything up to the start-up transformer?