Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Manhour Breakdown

Status
Not open for further replies.

shahyar

Chemical
Feb 15, 2005
216
I am wondering if there is such information:
For an EPCM project, in design phase (FEEd or whole from FEED to Detailed) we need 50,000 manhours.
How much percentage of that "used" by process group, how much by Mechanical, and the same question for I/C , Electerical, and Civil.

Thanks
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor