gegk
Materials
- Jan 29, 2009
- 22
We have in our specifications for the asphalt works the value marshall rigidity. This value is the result of Marshall stability/ flow and must be more than 250 for base course and more than 300 for binder. Because is the first project that we must check this value could somebody to give me more informations about this?
Thanks
Thanks