JAE
Structural
- Jun 27, 2000
- 15,575
The IBC states that the maximum length of an auger cast pile is 30 x diameter. For a 14" diameter pile, that is 35 feet. (see section 1810.3.2 of the 2006 IBC)
There is an exception to that where the IBC says that if a design professional with knowledge in the field of soil mechanics and pile foundation directly supervises the pile installation and certifies that they were constructed per the plans/documents, then it is OK to extend past the 30d limit.
Is this just a cautionary limit or are there major pitfalls with exceeding the 30d?
There is an exception to that where the IBC says that if a design professional with knowledge in the field of soil mechanics and pile foundation directly supervises the pile installation and certifies that they were constructed per the plans/documents, then it is OK to extend past the 30d limit.
Is this just a cautionary limit or are there major pitfalls with exceeding the 30d?