BINGMD
Electrical
- Jul 26, 2005
- 37
Background:
There are two 230kV stations within a same yard with a fence in between. Station 1 is a three 230kV breaker ring bus. Station 2 is a three winding transformer 230/115/34.5kV Yg/Yg/Delta with one 115kV line and one 34.5kV feeder. At delta tertiary, there is a grounding transformer to make the tertiary system effectively grounded.
Question is:
Both station 1 and station 2 grounding grids are tie together, so shall we consider 115kV and 34.5kV side ground fault levels while finding the maximum ground fault current for performing station 1 grounding grid calculation and design? If yes or no, any reference document to support?
Thank you,
Best Regards,
Bing
There are two 230kV stations within a same yard with a fence in between. Station 1 is a three 230kV breaker ring bus. Station 2 is a three winding transformer 230/115/34.5kV Yg/Yg/Delta with one 115kV line and one 34.5kV feeder. At delta tertiary, there is a grounding transformer to make the tertiary system effectively grounded.
Question is:
Both station 1 and station 2 grounding grids are tie together, so shall we consider 115kV and 34.5kV side ground fault levels while finding the maximum ground fault current for performing station 1 grounding grid calculation and design? If yes or no, any reference document to support?
Thank you,
Best Regards,
Bing