kbak47
Civil/Environmental
- Oct 8, 2019
- 5
We replaced the plates in a two cassette MBR with 100 plates each in March 2018. Within the last 3 months we have had to tie off multiple plates due to failures.
The TSS is kept between 11000 and 13000 mg/l. The daily flows are between 20000 and 30000 gals. We have the system set at about 25 gpm on a
3 minute permeate cycle and between a 60 to 180 second air scour depending on flows. This is at a mining camp and it is regular sewage being processed.
All products used that end up in the system are regulated so there are no harsh chemicals being put down the drain.
Any ideas about how to figure out the issues that would cause these failures.
The TSS is kept between 11000 and 13000 mg/l. The daily flows are between 20000 and 30000 gals. We have the system set at about 25 gpm on a
3 minute permeate cycle and between a 60 to 180 second air scour depending on flows. This is at a mining camp and it is regular sewage being processed.
All products used that end up in the system are regulated so there are no harsh chemicals being put down the drain.
Any ideas about how to figure out the issues that would cause these failures.