RHT2020
Structural
- Mar 24, 2019
- 12
Hi, I am designing a building for heavy overhead cranes(2 x 175 T). It is a conventional steel building with double column for crane runway beams. Each bent is designed as moment frame and I have vertical bracing in runway direction at every 4-5 bays. Also I have roof horizontal bracing to tie each bent together.
This building is pretty high (65’), the allowable drift due to crane is over 2” at roof level.
I have some questions:
1)My building looks like a “pre-eng” building, it seems I only have to select roof deck for gravity loads. Less stiff metal deck is better?
2)I feel I should use mechanical fastener for metal deck instead of puddle welds because pin connection are more ductile. And connection spacing should be as large as possible?
Please let me know if I am right or wrong.
Thanks.
This building is pretty high (65’), the allowable drift due to crane is over 2” at roof level.
I have some questions:
1)My building looks like a “pre-eng” building, it seems I only have to select roof deck for gravity loads. Less stiff metal deck is better?
2)I feel I should use mechanical fastener for metal deck instead of puddle welds because pin connection are more ductile. And connection spacing should be as large as possible?
Please let me know if I am right or wrong.
Thanks.